mbta-beverly-drawbridge-2-aug-2017As the work to replace the Beverly Drawbridge is about to finish on schedule, MBTA weekday Commuter Rail service will resume on Monday, August 14.

While regular Commuter Rail train times will be back in effect on August 14, Zone 3 monthly passes will continue to be accepted to and from all stations north of Salem Station through the end of August. Beginning September 1, Newburyport/Rockport Commuter Rail customers should resume purchasing the appropriate Zone 4-8 monthly passes where applicable.

The replacement of the Beverly Drawbridge will allow for more reliable service on the Newburyport/Rockport Line. When complete, the new swing-span bridge will be supported by the existing pivot pier. A new Electrical Room and Generator are also being constructed with the Control House being remodeled.

For more information on the project and the Newburyport/Rockport Line, please visit mbta.com.

Written By:

Tags:

Recent Posts

Natick: Marion Street Bridge Opens Ahead of Schedule posted on Dec 16

Natick: Marion Street Bridge Opens Ahead of Schedule

MassDOT is pleased to announce that the bridge that carries Marion Street over the MBTA railroad tracks in Natick reopened to vehicular and pedestrian traffic Friday, several months ahead of schedule. “We are proud of the hard work of our MassDOT crews and contractors who   …Continue Reading Natick: Marion Street Bridge Opens Ahead of Schedule

MassDOT, MBTA, Massport: Baker-Polito Administration Prepared for Winter Weather posted on Dec 15

MassDOT, MBTA, Massport: Baker-Polito Administration Prepared for Winter Weather

With the winter weather season beginning, Governor Charlie Baker today joined Highway Administrator Jonathan Gulliver, MBTA General Manager Luis Manuel Ramírez, Keolis CEO and General Manager David Scorey, and Massport CEO Thomas P. Glynn at a news conference in Somerville to highlight resiliency and preparedness   …Continue Reading MassDOT, MBTA, Massport: Baker-Polito Administration Prepared for Winter Weather

MBTA: FMCB Third Annual Report: T transformation “is gaining speed” posted on Dec 15

MBTA: FMCB Third Annual Report: T transformation “is gaining speed”

Less than three years after its near physical and organizational collapse, the MBTA’s transformation into a safe, reliable, and well-managed transit system “is gaining speed,” according to the Third Annual Report of the Fiscal and Management Control Board. The FMCB was created to govern the   …Continue Reading MBTA: FMCB Third Annual Report: T transformation “is gaining speed”