mbta-wollaston-construction-december-2017The MBTA announced its final plans relative to the closure of Wollaston Station, which will begin on January 8. The closure is necessary to expedite the schedule to reconstruct the deteriorated station.

Transportation Secretary and CEO Stephanie Pollack, MBTA General Manager Luis Manuel Ramírez, Senator John Keenan, Quincy Mayor Thomas Koch, other state elected official, and members of the Quincy City Council gathered to discuss customer accommodations during the station closure.

“Safety is the priority as we replace Wollaston Station,” said Secretary Pollack. “Red Line trains will continue to be provided along the Red Line, but the trains will not stop at Wollaston in the interest of the safety of our customers. We believe we have a comprehensive and efficient plan in place to continue to help customers get to where they need to go, as bus shuttles will operate out of the station and parking will still be available.”

Working in coordination with city officials, T customers, and Wollaston residents, the T will be operating bus shuttle service from Wollaston to both North Quincy and Quincy Center Stations for the twenty months that the station is closed. While the Wollaston parking lot will see a reduction of approximately 110 spaces, T customers can continue to use the remaining approximately 425 spaces in that lot. Parking is also available at North Quincy, which can be accessed via Newport Avenue.

Additionally, for the duration of the closure of Wollaston, the T is accepting Zone 1A fares at Quincy Center for those customers desiring to board the commuter rail with valid passes or tickets accepted. In anticipation of the increase in Commuter Rail riders, additional seating capacity will be made available on the Greenbush, Kingston/Plymouth, and Middleborough/Lakeville Lines, which pass through Quincy Center.

“Working in collaboration with the city and elected officials, and in response to community concerns about the closure’s timing, we’ve decided to move the closure date to January 8 to give our customers more time to plan ahead,” said MBTA General Manager Ramírez. “While we recognize that the station closure will be an inconvenience to our customers now, in the long run, we’ll be able to complete this project under an expedited schedule and with our customers’ safety in mind. I want to thank the city of Quincy for their partnership and I look forward to transforming Wollaston into a modern and fully accessible station.”

“Today marks a crucial step forward for the Wollaston Station Improvement project. The mitigation plan released today reflects months of communication between state and local officials, members of the public, MassDOT, and the MBTA,” said State Senator John Keenan. “We are committed to continuing our work in order to mitigate disruptions to commuters. The reconstruction of Wollaston Station, combined with a new Red Line fleet and updated signalization, will provide commuters with a reliable and efficient transportation system.”

In advance of the station’s closure, a bus shuttle began operating Sundays through Thursdays starting November 12 from 9 p.m. through the end of service between North Quincy and Braintree Stations. This shuttle service allows for ongoing early construction activities in an effort to expedite the overall reconstruction.

Some of the Wollaston improvements include major accessibility enhancements, state-of-the-art safety features, and new drainage and flood prevention infrastructure. Currently the only non ADA-accessible station on the Red Line, Wollaston will be transformed into a modern, fully accessible facility, making the entirety of the Red Line 100-percent accessible. Additional upgrades to the station include new elevators, additional customer paths, upgraded stairways, new bathrooms, and additional lighting. New electrical, fire protection, security, flooding mitigation, and site utility upgrades will also occur to support the accessible improvements. The estimated construction value of the Wollaston Station Improvements is $33 million.

Meanwhile, the MBTA is improving infrastructure at other station locations. Demolition work at the Quincy Center Station Garage, which was closed in July 2012 due to structural concerns, is also scheduled to begin in early 2018. As part of the work at Quincy Center Station, the existing elevator will be completely replaced and an accessible entrance at Burgin Parkway will be added. Construction of the project will occur through December 2018 for a construction value of $13 million. The station will remain open and fully functional during construction.

Additional Red Line south shore upgrades are also planned at the Braintree and Quincy Adams parking garages. Renovations to the garages at these stations will bring the facilities to a state of good repair with an anticipated useful life of forty years, improve accessibility, and provide for more efficient and improved parking layout. Included are structural repairs, replaced drainage systems, upgraded fire alarm, CCTV, electrical, and emergency power systems, and full replacement of lighting systems. Accessibility upgrades include two new elevators at Braintree Garage as well as improvements to both garages in wayfinding signage and better traffic circulation for accessibility vehicles, wheelchair access, and pedestrian movement. Construction of both garages is anticipated to begin in early 2018 with an estimated construction contract value of $90 million. Both garages will remain in service during the construction period. This work will be advertised for construction next week.

The MBTA has committed $911 million to Red Line south shore projects, including 252 new Red Line cars that will begin full revenue service in November 2019. The renovations at Wollaston Station are a major part of a series of signal, rail, and other infrastructure upgrades along the Red Line. Previous MBTA successes in renovation construction with station shutdowns include Government Center, Orient Heights, and Science Park Stations.

For more information on the Wollaston Station Improvements Project, please visit the project webpage.

 

Written By:

Tags:

Recent Posts

MassDOT: Memorial Day Advisory posted on May 21

MassDOT: Memorial Day Advisory

MassDOT is urging the public to stay home Memorial Day Weekend to comply with the Reopening Advisory Board’s “Safer-at-Home-Advisory.”  The Advisory states, in part: all residents should leave home only for healthcare, worship and permitted work, shopping and outdoor activities; people over the age of   …Continue Reading MassDOT: Memorial Day Advisory

MBTA: Year-Long Green Line Closure between Lechmere and North Stations Begins Sunday posted on May 20

MBTA: Year-Long Green Line Closure between Lechmere and North Stations Begins Sunday

The MBTA today reminded customers that Green Line service between Lechmere and North Stations is replaced with shuttle buses every day beginning at the start of service on Sunday, May 24, for approximately one year to accomplish work as part of the Green Line Extension   …Continue Reading MBTA: Year-Long Green Line Closure between Lechmere and North Stations Begins Sunday

MBTA to Install Bus-Only Pavement Markings on Charles River Dam Road beginning Monday, May 18 posted on May 15

MBTA to Install Bus-Only Pavement Markings on Charles River Dam Road beginning Monday, May 18

The MBTA announced today that work to install bus-only pavement markings for temporary dedicated bus lanes on Charles River Dam Road will begin on Monday, May 18. In effect for approximately one year beginning Sunday, May 24, the dedicated bus lanes will support bus replacement   …Continue Reading MBTA to Install Bus-Only Pavement Markings on Charles River Dam Road beginning Monday, May 18