Methuen Bridge Open 2 18NOV09 As part of the Patrick-Murray Administration’s Massachusetts Recovery Plan to secure the state’s economic future, Transportation Secretary and CEO Jeffrey Mullan today announced the reopening of the Route 28 over Route 213 bridge replacement project in Methuen, a streamlined MassDOT Highway Division project substantially completed 17 months ahead of the original schedule.

“Our team is committed to the kind of innovation and hard work that makes achievements like this expedited bridge opening possible,” said Governor Deval Patrick. “We are completing projects ahead of schedule here in Methuen and across the Commonwealth, and that’s great news for our residents and businesses.”

The $10 million project involved complete replacement of the four-lane Route 28 (Broadway) bridge over Route 213. Crews earlier this summer demolished the existing bridge and constructed a new two-span steel superstructure bridge with five-foot sidewalks. 

MassDOT Highway Division working with the contractor S & R Corporation, Lowell, streamlined the project by using two temporary bridges for traffic, allowing the work to be completed in a single stage.  This move reduced the work schedule by a full year with opening expected in April 2010 rather than 2011.  However, work progress continued at a quicker than expected pace and the bridge has now opened 17 months earlier than first planned.

While delivering more projects, the MassDOT Highway Division has reduced consultant procurement times from 18 months to 5.7 months and reduced construction procurement time by 45 percent.  MassDOT continues to reform design and construction timelines, including an aggressive program to reduce the time it takes to reconstruct and rehabilitate bridges, and has entered agreements with environmental agencies to streamline the permitting process.  Learn more about MassDOT's Highway Division projects.

Written By:

Recent Posts

Baker-Polito Administration Celebrates “Open for Business” Housing Project in Truro posted on Oct 19

Baker-Polito Administration Celebrates “Open for Business” Housing Project in Truro

Lieutenant Governor Karyn Polito, the Massachusetts Department of Transportation (MassDOT), state legislators and municipal officials from the Town of Truro, today celebrated the transfer of a 3.91 acre underutilized state-owned parcel to Truro for the development of affordable housing opportunities for year-round, lower-income residents of   …Continue Reading Baker-Polito Administration Celebrates “Open for Business” Housing Project in Truro

Methuen Rotary Project: I-93 New Exit 46B Now Open posted on Oct 18

Methuen Rotary Project: I-93 New Exit 46B Now Open

MassDOT today opened the new off-ramp (Exit 46B) from I-93 northbound to Route 110/113 westbound. This significant construction milestone is one aspect of the ongoing Methuen Rotary Reconstruction Project.  The new off-ramp from I-93 northbound is located just north of the new bridge carrying I-93   …Continue Reading Methuen Rotary Project: I-93 New Exit 46B Now Open

Champion Officially Joins MBTA Ferry Fleet posted on Oct 18

Champion Officially Joins MBTA Ferry Fleet

On October 18, the MBTA celebrated the upcoming addition of its brand new catamaran ferry, the Champion, with a boat christening ceremony of the new ferry by MBTA General Manager Luis Manuel Ramírez. Ramírez also met with the new vessel’s crew and MBTA ferry management   …Continue Reading Champion Officially Joins MBTA Ferry Fleet