Post Content

Methuen Bridge Open 2 18NOV09 As part of the Patrick-Murray Administration’s Massachusetts Recovery Plan to secure the state’s economic future, Transportation Secretary and CEO Jeffrey Mullan today announced the reopening of the Route 28 over Route 213 bridge replacement project in Methuen, a streamlined MassDOT Highway Division project substantially completed 17 months ahead of the original schedule.

“Our team is committed to the kind of innovation and hard work that makes achievements like this expedited bridge opening possible,” said Governor Deval Patrick. “We are completing projects ahead of schedule here in Methuen and across the Commonwealth, and that’s great news for our residents and businesses.”

The $10 million project involved complete replacement of the four-lane Route 28 (Broadway) bridge over Route 213. Crews earlier this summer demolished the existing bridge and constructed a new two-span steel superstructure bridge with five-foot sidewalks. 

MassDOT Highway Division working with the contractor S & R Corporation, Lowell, streamlined the project by using two temporary bridges for traffic, allowing the work to be completed in a single stage.  This move reduced the work schedule by a full year with opening expected in April 2010 rather than 2011.  However, work progress continued at a quicker than expected pace and the bridge has now opened 17 months earlier than first planned.

While delivering more projects, the MassDOT Highway Division has reduced consultant procurement times from 18 months to 5.7 months and reduced construction procurement time by 45 percent.  MassDOT continues to reform design and construction timelines, including an aggressive program to reduce the time it takes to reconstruct and rehabilitate bridges, and has entered agreements with environmental agencies to streamline the permitting process.  Learn more about MassDOT's Highway Division projects.

Written By:

Recent Posts

Fore River Bridge Project Milestone posted on Jul 29

Fore River Bridge Project Milestone

The Fore River Bridge Replacement Project in Quincy-Weymouth continues during the summer of 2014 with installation of the permanent bridge components along with a new milestone: arrival of the new bridge steel sections. The view above shows the progress made at the Quincy tower location.   …Continue Reading Fore River Bridge Project Milestone

Green Line Extension: Public Meeting July 31 posted on Jul 28

Green Line Extension: Public Meeting July 31

A City of Somerville and MBTA Green Line Extension Public Meeting regarding Medford Street Bridge construction has been scheduled for the following: Thursday, July 31, 6:00pm, Public Safety Building, 220 Washington Street, Somerville. Green Line Extension construction is underway and will involve periodic traffic impacts   …Continue Reading Green Line Extension: Public Meeting July 31

MBTA: New WiFi System Announced posted on Jul 24

MBTA: New WiFi System Announced

Under a new license agreement signed today by MBTA General Manager Beverly Scott, a state-of-the-art WiFi system will be installed throughout the MBTA’s sprawling network of fourteen Commuter Rail lines. At no cost to the MBTA or its customers, inMOTION Wireless, Inc. will build a   …Continue Reading MBTA: New WiFi System Announced