Murray_tim_764Lieutenant Governor Timothy Murray this week released a progress report, “Transforming the Rail Network for Economic and Community Development”, describing accomplishments achieved as a result of the historic agreement with CSX Corporation.

“Transportation is the enabling network of our economy – it’s about getting people and businesses from one location to another,” said Lieutenant Governor Murray. “I have worked closely with many critical partners and stakeholders to advance the CSX agreement and invest in improved freight and commuter rail service. This progress report outlines how our rail system is evolving across the state, and simultaneously highlights the need to have continued conversations to enhance economic and community development in impacted regions.”

Improving the state’s transportation infrastructure has been a key priority of the Patrick-Murray Administration. As part of the Massachusetts State Rail Plan, the Administration has strategically invested close to $1 billion in the state’s rail system through competitive grants, public funds and private sector capital. These investments, some ongoing, represent the most significant improvements in the Commonwealth’s rail system as a whole in decades.

The historic agreement with CSX Corporation offers significant impacts to freight and rail service in Central Massachusetts, Metrowest, Western Massachusetts, Boston and South Coast regions.  The compact is being finalized in two parts, beginning with an initial closing in June of 2010, which set in motion the permitting processes and infrastructure work needed to allow for the relocation of CSX operations.

The second closing, scheduled for early October will complete the full transaction.  Details after the break.

The second closing will allow for:

  • Expanding commuter rail service to the Metrowest/Worcester areas by taking ownership and control of the rail line between Framingham and Worcester.
  • Raising the railroad bridge clearances from Westborough to the New York State line to allow, for the first time in state history, the double-stacking of full-size freight containers on trains serving Massachusetts. This will increase freight capacity, reduce costs, and give Massachusetts companies better access to national and Asian markets.
  • Making possible the eventual restoration of commuter rail service to the South Coast by taking ownership of the rail lines that run from Boston to New Bedford and Fall River.
  • Relocating the CSX freight rail operations now in Boston at the Beacon Park Yard, to rail yards in Westborough, Worcester and West Springfield. This relocation will allow for the redevelopment of an 80+- acre parcel along the Charles River to serve as a new gateway district for the city.

With the second closing, the full transaction will be complete and the Commonwealth will pay CSX $100 million in total for:

  • 45 miles of the Framingham/Worcester Commuter Rail line between Boston and Worcester
  • 37 miles of rail lines running south from Taunton to Fall River and New Bedford
  • 8 miles known as the Grand Junction, which runs from Allston, across the Charles River, through Cambridge, Charlestown, Everett and Chelsea
  • 2 miles known as the Boston Terminal Running Track which extends from Dorchester to South Boston, including the West First Street Yard

As part of this public-private partnership, CSX is investing $129 million for rail yards in Worcester, Westborough and West Springfield to expand and enhance freight services throughout the Commonwealth. The Commonwealth and CSX have also worked together to complete bridge work at 31 locations across the state, from the New York border to Worcester, to raise the clearance to allow for the double-stacking of full-size freight containers. Through this initiative, the Massachusetts Department of Transportation has raised clearances at 14 of those locations by investing $72 million and CSX has completed the work for the remaining sites.

Written By:

Recent Posts

Labor Day Weekend Travel: Plan Ahead! posted on Aug 27

Labor Day Weekend Travel: Plan Ahead!

MassDOT encourages motorists to plan ahead for safe travel during the upcoming Labor Day holiday weekend. Heaviest Labor Day traffic on I-90 is expected Thursday and Friday westbound and Monday afternoon-evening eastbound.  The number of toll transactions on the Turnpike from Weston to the New   …Continue Reading Labor Day Weekend Travel: Plan Ahead!

Boston: I-90 Construction Update posted on Aug 26

Boston: I-90 Construction Update

MassDOT contractors in August and September continue the preparation work to improve the median and Commonwealth Avenue Bridge substructure on Interstate 90 in Boston. The left lanes in both Eastbound and Westbound directions on I-90 from west of the Prudential tunnel to the Commonwealth Avenue   …Continue Reading Boston: I-90 Construction Update

Braintree-Weymouth Route 3 Resurfacing Begins September 2 posted on Aug 25

Braintree-Weymouth Route 3 Resurfacing Begins September 2

MassDOT Secretary Richard A. Davey in Braintree today announced that the Route 3 Resurfacing Project in Weymouth and Braintree will begin Tuesday night, September 2. Paving work will occur from Exit 16/Route 18 in Weymouth to the Route 3 connection with I-93 North and South   …Continue Reading Braintree-Weymouth Route 3 Resurfacing Begins September 2