Weston Bridge Open 23OCT09 MassHighway today opened the new two-span bridge carrying Recreation Road in Weston over I-95/Route 128. 

The $3.5 million bridge replacement began with demolition last year of the existing bridge.  New high performance concrete bridge beams were erected this spring by contractors SPS New England, Inc. of Salisbury. 

The bridge opened today, a full six weeks ahead of original schedule.

Learn more about MassHighway road and bridge projects underway across the Commonwealth.

Written By:

Recent Posts

Casey Arborway Project Public Meeting Set posted on Jun 24

Casey Arborway Project Public Meeting Set

MassDOT has scheduled a fourth Casey Arborway Project Construction Update Meeting as follows: Wednesday, June 29, 6:30-8:30 PM, Boston English High School Auditorium 144 McBride Street, Jamaica Plain The purpose of this meeting will be to provide the community with an update on the progress   …Continue Reading Casey Arborway Project Public Meeting Set

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration posted on Jun 23

Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

MassDOT announced that the restoration of the iconic “salt and pepper” towers of the historic Longfellow Bridge will be complete in late July. The downstream towers have been replaced on the bridge, and barges are transporting the last stones for installation on them. The capstones   …Continue Reading Milestone Nears: Longfellow Bridge “Salt and Pepper” Towers Restoration

New Tunnels Gantry Infrastructure to be Installed posted on Jun 22

New Tunnels Gantry Infrastructure to be Installed

MassDOT has announced that new infrastructure for two vertical gantry supports on the East Boston sides of the Sumner and Callahan Tunnels will begin to be installed late tonight, June 22.  Installation work will continue during off-peak hours during the next several days with gantries   …Continue Reading New Tunnels Gantry Infrastructure to be Installed