Post Content

Whittier Bridge, August 8, 2013MassDOT contractors for the Whittier Bridge/I-95 Improvement Project will continue work during the weeks of December 22 and December 29. No work will be performed on Christmas Day, December 25, and New Year’s Day, January 1.

The work will require daytime lane single lane closures on I-95 northbound and southbound throughout the project limits. Should nighttime closures be necessary, they would be single or multiple lanes, depending on the location.

A single lane closure on I-95 northbound from the on-ramp at Route 113 to just north of the off-ramp for Route 110 west will be in place most work days from 7 AM to 5 PM through 2014. The closure is necessary for the contractor to build the new I-95 northbound alignment. The lane closure hours will be 7 AM to 5 PM, Monday through Thursday, and 7 AM to 3 PM on Fridays and Saturdays.

Work including the following:

Week of December 22:

I-95 at northern end of project

  • Drainage system construction – 7 AM to 3:30 PM

Evans Place between Elm Street and I-95

  • Utility relocations – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM
  • Retaining wall “E” construction – 7 AM to 5 PM

I-95 at southern end of project

  • Embankment construction – 7 AM to 5 PM
  • Drain line installation – 7 AM to 5 PM

Whittier Bridge

  • Install pile caps and footings at Pier 3 – 7 AM to 5 PM
  • Install mini-piles at Pier 2 – 7 AM to 5 PM
  • Pile, footing and tower installation in river and on shorelines for support during intermediate stages of bridge erection – 7 AM to 5 PM

Evans Place Bridge

  • Drilled shaft installation – 7 AM to 5 PM
    • Lane restrictions – one alternating travel lane with a police detail officer

Railroad Bridge

  • Install support of excavation and begin excavation – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Retaining wall “D” construction – 7 AM to 3:30 PM
  • Abutment wall installation for support of bridge deck – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Footing installation – 7 AM to 5 PM

Week of December 29:

 

I-95 at northern end of project

  • Drainage system construction – 7 AM to 3:30 PM

I-95 northbound between Evans Place to Route 110

  • Earth/rock excavation – 7 AM to 5 PM
  • Retaining wall “E” construction – 7 AM to 5 PM

I-95 at southern end of project

  • Embankment construction – 7 AM to 5 PM
  • Drain line installation – 7 AM to 5 PM

Whittier Bridge

  • Install pile caps and footings at Pier 3 – 7 AM to 5 PM
  • Install mini-piles at Pier 2 – 7 AM to 5 PM
  • Pile and tower installation in river and on shorelines for support during intermediate stages of bridge erection – 7 AM to 5 PM

Evans Place Bridge

  • Drilled shaft installation – 7 AM to 5 PM
  • Lane restrictions – one alternating travel lane with a police detail officer

Railroad Bridge

  • Install support of excavation and begin excavation – 7 AM to 5 PM

I-95 northbound immediately north of Whittier Bridge

  • Retaining wall “D” construction – 7 AM to 3:30 PM
  • Abutment wall installation for support of bridge deck – 7 AM to 5 PM

I-95 northbound immediately south of Whittier Bridge

  • Abutment wall installation for support of bridge deck – 7 AM to 5 PM

Written By:

Recent Posts

Tobin Bridge/Chelsea Curves Rehabilitation Project Update posted on Aug 15

Tobin Bridge/Chelsea Curves Rehabilitation Project Update

MassDOT has announced that the lane closures and roadway configuration on Route 1 northbound in Chelsea will shift on Monday, August 19 so that the center lane on this section of highway will be closed 24/7. Both the right and left travel lanes will be   …Continue Reading Tobin Bridge/Chelsea Curves Rehabilitation Project Update

First New MBTA Orange Line Cars Enter Passenger Service posted on Aug 14

First New MBTA Orange Line Cars Enter Passenger Service

Governor Charlie Baker, MassDOT Secretary and CEO Stephanie Pollack, and MBTA General Manager Steve Poftak today introduced the first new Orange Line train comprised of six brand new cars into regular service from Wellington Station. These six new cars entering passenger service today are the   …Continue Reading First New MBTA Orange Line Cars Enter Passenger Service

MBTA Announces Accelerated Schedule for System Upgrades, Cuts Project Timelines posted on Aug 12

MBTA Announces Accelerated Schedule for System Upgrades, Cuts Project Timelines

The MBTA today announced several planned system upgrade construction projects will be accelerated, shortening some timelines by as much as eleven months for certain projects. System upgrade work to improve reliability for riders on the Green, Red, and Orange Lines that was previously scheduled to   …Continue Reading MBTA Announces Accelerated Schedule for System Upgrades, Cuts Project Timelines