Longfellow Bridge: New Permanent Outbound MBTA Red Line Track

Longfellow Bridge: New Permanent Outbound MBTA Red Line Track

Due to the Longfellow Bridge Rehabilitation Project, shuttle buses will replace Red Line trains in both directions between Park Street and Kendall/MIT Stations, with a stop at Charles/MGH Station, on weekends beginning on Saturday, September 30, through Sunday, December 17. The bus route and stops are shown on this map.

The Longfellow Bridge will also be closed to all private and commercial vehicular traffic on these weekends when work is taking place, with access maintained for bus shuttles, emergency vehicles, bicyclists, and pedestrians. The bridge is currently scheduled to be open and Red Line trains will be in use for the Head of the Charles weekend (October 21-22) and Thanksgiving weekend (November 25-26).

On each weekend, the use of bus shuttles will begin at the start of service on Saturday and will end at the beginning of service on Monday, and the Longfellow Bridge will be closed to all vehicular traffic from 11:00 PM each Friday to 5:00 AM the following Monday.

Bus shuttles and emergency responders will be the only motor vehicles permitted on the bridge. Bicyclists, both inbound and outbound, and pedestrians will use the shared upstream sidewalk during the work. All other motor vehicles, including passenger vehicles and trucks, will need to use one of two Boston-bound routes to reach Charles River Dam Road (Monsignor O’Brien Highway/Route 28) and Leverett Circle.

Inbound Detour Routes: Height restrictions are in place for Memorial Drive, so all buses and trucks must use the 3rd Street to Binney Street detour described below.

  • From Main Street, turn right onto Memorial Drive westbound, and make a U-turn at Ames Street to access Memorial Drive eastbound. Follow Memorial Drive eastbound to Land Boulevard and turn right onto Charles River Dam Road (Monsignor O’Brien Highway/Route 28) to reach Leverett Circle.
  • From Broadway, turn left onto 3rd Street, turn right on Binney Street, turn left onto Land Boulevard, and then turn right onto Charles River Dam Road (Monsignor O’Brien Highway/Route 28) to reach Leverett Circle.

The Cambridge-bound detour remains in place using a signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway/Charles River Dam Road, and Edwin H. Land Boulevard.

During these weekends, elements below the Red Line’s right of way will be replaced, which requires the removal and replacement of all Red Line track systems near Charles/MGH Station. The replacement of the track may also require some speed restrictions in this area of the Red Line for the days immediately following each weekend.

For more information on the project, visit the project website. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album. For questions or to report issues related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us.

Written By:

Tags: ,

Recent Posts

MBTA: Draft Public Engagement Plan and Upcoming Public Meetings posted on Jan 28

MBTA: Draft Public Engagement Plan and Upcoming Public Meetings

The MBTA has announced the availability of its draft Public Engagement Plan as well as a series of public meetings intended to introduce the public to the draft Plan and solicit public feedback. With the engagement of the public as critical in the development and   …Continue Reading MBTA: Draft Public Engagement Plan and Upcoming Public Meetings

MBTA: Major Green Line Extension Work Coming in Spring 2020 posted on Jan 28

MBTA: Major Green Line Extension Work Coming in Spring 2020

The MBTA announced major work taking place this spring 2020 on the Green Line as part of the Green Line Extension project (GLX) and the Green Line Transformation Program (GLT): the closure, relocation, and complete replacement of Lechmere Station to take place for approximately one   …Continue Reading MBTA: Major Green Line Extension Work Coming in Spring 2020

Baker-Polito Administration, Federal & Local Officials Celebrate Improvements at Springfield’s Union Station posted on Jan 24

Baker-Polito Administration, Federal & Local Officials Celebrate Improvements at Springfield’s Union Station

Governor Charlie Baker, Congressman Richard Neal, Springfield Mayor Domenic Sarno, MassDOT officials, legislators and other local officials today celebrated recently-completed improvements at Springfield’s Historic Union Station to Platform C. The $10 million project built a fully ADA-accessible 328-foot long high-level platform accessing two tracks, and   …Continue Reading Baker-Polito Administration, Federal & Local Officials Celebrate Improvements at Springfield’s Union Station