Post Content

Ted Williams Tunnel As of today, MassDOT crews as a safety measure have completed installation of redundant support straps on  all of the approximately 25,000 fixtures in the Central Artery tunnels.  This system was developed as an interim, 3-5 year solution to the light corrosion issues while engineers evaluate options for a long-term solution.

On July 14, a MassDOT engineer observed a light fixture out of alignment with the clips on the right side of the light not secured.  The fixture was removed immediately and on July 15 re-installed with all new stainless steel clips.  In addition, two high-strength straps were installed as a redundant support measure.

MassDOT crews had already begun the process of installing the redundant support straps on all of the approximately 25,000 tunnel light fixtures at the time of the July 14 discovery.

Following the July 14 discovery, Secretary Mullan ordered an acceleration of the installation of the redundant support fix for all fixtures.  The intensified installation effort added outside contractors to the in house crews already working on this issue. 
   
The Secretary had committed to completion of the redundant system installation by early August.  To achieve this aggressive schedule, MassDOT mobilized additional lifts and electricians.  While the crews worked throughout the tunnel system, an early emphasis was placed on the ramps and entry portal areas. 

We thank commuters for their patience during the lane restrictions in non-peak traffic hours to support this work. 

The MassDOT Tunnel Safety page on the web provides the latest information about ongoing steps to ensure the tunnel system remains safe.

Written By:

Recent Posts

Update on Massachusetts Motor Vehicle Inspections posted on Apr 17

Update on Massachusetts Motor Vehicle Inspections

The following is an update from the Massachusetts Registry of Motor Vehicles (RMV) with regard to vendor Applus Technologies (Applus) nationwide vehicle inspection system outage.

MassDOT, Boston Properties Highlight New Operational and Safety Improvements at Route 128/Interstate 95 Interchange Ramp and Roadways in Waltham posted on Apr 14

MassDOT, Boston Properties Highlight New Operational and Safety Improvements at Route 128/Interstate 95 Interchange Ramp and Roadways in Waltham

The Massachusetts Department of Transportation (MassDOT) in conjunction with Boston Properties (NYSE: BXP) is pleased to announce that new operational and safety improvement modifications have been implemented at the Route 128/Interstate 95 Interchange 43A (Old Exit 27A)/Third Avenue ramp in Waltham. The purpose of this transportation improvement project was to redesign this heavily traveled interchanges and the immediately surrounding area to improve existing traffic flow operations, to enhance safety for motorists, pedestrians, and bicyclists, and to provide improved access for the future mixed-use development of up to 1.85 million square feet located within the adjacent CityPoint and 1265 Main developments.

MassDOT Advisory: Statewide Exit Renumbering Project posted on Mar 2

MassDOT Advisory: Statewide Exit Renumbering Project

BOSTON – The Massachusetts Department of Transportation (MassDOT) is announcing that it will begin installing new milepost-based signs for all exits on Interstate 91, from the Vermont border to the Connecticut border, tomorrow, Wednesday, March 3.  The milepost sign installation operations will take place during   …Continue Reading MassDOT Advisory: Statewide Exit Renumbering Project