Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

Tobin Bridge/Chelsea Curves Rehabilitation Project Update posted on Aug 15

Tobin Bridge/Chelsea Curves Rehabilitation Project Update

MassDOT has announced that the lane closures and roadway configuration on Route 1 northbound in Chelsea will shift on Monday, August 19 so that the center lane on this section of highway will be closed 24/7. Both the right and left travel lanes will be   …Continue Reading Tobin Bridge/Chelsea Curves Rehabilitation Project Update

First New MBTA Orange Line Cars Enter Passenger Service posted on Aug 14

First New MBTA Orange Line Cars Enter Passenger Service

Governor Charlie Baker, MassDOT Secretary and CEO Stephanie Pollack, and MBTA General Manager Steve Poftak today introduced the first new Orange Line train comprised of six brand new cars into regular service from Wellington Station. These six new cars entering passenger service today are the   …Continue Reading First New MBTA Orange Line Cars Enter Passenger Service

MBTA Announces Accelerated Schedule for System Upgrades, Cuts Project Timelines posted on Aug 12

MBTA Announces Accelerated Schedule for System Upgrades, Cuts Project Timelines

The MBTA today announced several planned system upgrade construction projects will be accelerated, shortening some timelines by as much as eleven months for certain projects. System upgrade work to improve reliability for riders on the Green, Red, and Orange Lines that was previously scheduled to   …Continue Reading MBTA Announces Accelerated Schedule for System Upgrades, Cuts Project Timelines