Photo 4(5)MassDOT’s contractor, White-Skanska-Consigli (WSC), anticipates setting up the final configuration of Stage 3 construction for the Longfellow Bridge Rehabilitation Project by Thursday, February 11, 2016. The shift of the tracks to their temporary positions was completed over a series of MBTA Red Line Weekend Diversions. The relocation of the large barrier fence along the tracks will be completed February 1.

The installation of the upstream “Salt and Pepper” towers, hampered by the cold temperatures of mid-January, is complete with the last stones installed. Now that the towers are complete, removal of the staging is underway, followed by the placement of concrete sidewalks and curbs adjacent to the towers. Once the sidewalks and curbs are in place, the final sections of temporary fence needed for the new upstream bicycle lane can be installed.

WSC anticipates the final set up for the upstream bicycle lane will be complete by the end of the day on Thursday, February 11, 2016, when inbound and outbound bike travel is shifted. Stage 3 work will take approximately eight months to complete.

Travel Configuration

All bike travel, both inbound and outbound, will be shifted to the sidewalk on the upstream side of the bridge on February 11. During this stage, inbound vehicles and all pedestrians will continue to use the downstream side of the bridge.

MBTA Red Line Configuration

The construction of the temporary outbound Red Line track (called a “shoo-fly”) on the roadway is complete. The outbound trains were shifted to the shoo-fly track and the inbound trains were shifted to the old outbound track in mid-January. This shift allows WSC to rehabilitate the bridge under the current location of the MBTA inbound tracks.

The Cambridge-bound detour remains in place using the existing signed route from Charles Circle following Charles Street to Leverett Circle, Monsignor O’Brien Highway (Route 28)/Charles River Dam Road and Land Boulevard.

For more information, visit the project website at www.mass.gov/massdot/longfellowbridge. For questions or issues and concerns related to construction, please call the project hotline at 617-519-9892 or email longfellowbridge@state.ma.us. View construction progress photos on MassDOT’s Longfellow Bridge Flickr Album.

Written By:

Tags: ,

Recent Posts

MassDOT, MBTA Five-Year $18.3 Billion Capital Investment Plan Approved posted on Jun 17

MassDOT, MBTA Five-Year $18.3 Billion Capital Investment Plan Approved

The Massachusetts Department of Transportation Board of Directors and MBTA Fiscal Management and Control Board today voted to approve the five-year $18.3 billion MassDOT and MBTA Capital Investment Plan (CIP) for Fiscal Years 2020-2024, an increase of approximately $1 billion over the last five-year CIP.   …Continue Reading MassDOT, MBTA Five-Year $18.3 Billion Capital Investment Plan Approved

MassDOT Announces Annual Safe Streets Smart Trips High School Video Contest posted on Jun 17

MassDOT Announces Annual Safe Streets Smart Trips High School Video Contest

MassDOT is announcing the sixth annual statewide high school video contest, Safe Streets Smart Trips. The contest serves as an initiative within the Massachusetts Strategic Highway Safety Plan to promote and educate the public about safe walking, bicycling, and driving behaviors. The contest began five   …Continue Reading MassDOT Announces Annual Safe Streets Smart Trips High School Video Contest

Braintree: Adaptive Signal Control Technology Installation posted on Jun 14

Braintree: Adaptive Signal Control Technology Installation

MassDOT has announced that crews will begin installing Adaptive Signal Control Technology (ASCT) at seven intersections on Route 37 in Braintree the week of Monday, June 17. ASCT is a modern approach to traffic signal operation that allows individual traffic signals to automatically adjust to   …Continue Reading Braintree: Adaptive Signal Control Technology Installation